Activity C of a Project Has a Budgeted Cost of $40,000

question 137

Short Answer

Activity C of a project has a budgeted cost of $40,000 and is 20% complete.The actual cost is $10,000.
(a)What is the value of work completed?
(b)What is the activity difference?