A manufacturing work cell has a takt time of 7 minutes and is staffed by 10 workers. If the work cell delivers 68 units each day find
A. The total operation time
B. The amount of time worked during the day for all 10 workers combined
C. If the plant is open for only 8 hours per day, can the staff meet demand?


Definitions:

Stronger Future

A vision or strategy aimed at achieving greater success, resilience, and sustainability in the coming years.

Temporary Employment

Employment situations where individuals are hired for a specific, limited period of time, often to fill in for absent staff or to handle extra work.

Affirmative Action

Policies or practices that are intended to increase opportunities for historically underrepresented groups within education or employment sectors.

Temporary Workers

Individuals employed for a limited period to fulfill short-term business needs, often without the expectation of long-term employment.

Related Questions