question 26

Multiple Choice

Colson Corp.has planned a simple project with four tasks.The task information for the project is shown below: Colson Corp.has planned a simple project with four tasks.The task information for the project is shown below:   What is the estimated completion time for the project? A) 29 days B) 25 days C) 22 days D) 19 days What is the estimated completion time for the project?