A company needs to manage a project which consists of the following set of activities: Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   -Refer to Exhibit 15.4. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?
-Refer to Exhibit 15.4. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?


Definitions:

Mitigation Planning

A strategic approach to lessen the severity and impact of potential risks and disasters on a project or organization.

Strategic Planning

The process of defining an organization’s direction and making decisions on allocating its resources to pursue this strategy.

Functional Planning

pertains to the process of developing detailed strategies and actions for specific functional areas within an organization, such as marketing or operations.

Production Planning

The process of organizing and controlling all aspects of production, from raw material procurement to the final product, to ensure efficiency and productivity.