A Project Has Four Activities: A, B, C, and D

question 41

Multiple Choice

A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for Activity C?


Definitions:

Price Elasticity

The quantification of demand elasticity for a product relative to the shifts in its price.

Total Expenditures

The sum total of all spending or expenses incurred by an individual, business, or government.

Demand Curve

A graphical representation that shows the relationship between the price of a good and the quantity demanded by consumers, typically downward sloping.

Price Elasticity

The measure of how much the quantity demanded of a good responds to a change in the price of that good.

Related Questions