The Operations Manager of a Body and Paint Shop Has

question 1

Multiple Choice

The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:
The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:   What is the makespan for the optimal schedule? A) 24 hours B) 25 hours C) 26 hours D) 28 hours E) 50 hours
What is the makespan for the optimal schedule?


Definitions:

Conceptual Art

An American avant-garde art movement of the 1960s whose premise was that the “artfulness” of art lay in the artist’s idea rather than its final expression.

Judy Chicago

Judy Chicago is an American feminist artist, art educator, and writer known for her large-scale, collaborative art installation pieces that examine women's roles and experiences.

The Dinner Party

An installation artwork by American artist Judy Chicago, showcasing a large triangular table with place settings for 39 significant women in history.

Found Objects

Everyday objects found by artists and repurposed in art, often transcending their original mundane uses to acquire new meanings and aesthetics.

Related Questions