Simple Project Listing of Five Activities,their Predecessors,and Their Respective Time

question 17

Multiple Choice

simple project listing of five activities,their predecessors,and their respective time estimates are presented below:
simple project listing of five activities,their predecessors,and their respective time estimates are presented below:   Using the CPM,which activities have slack in this project? A) A B) B C) C D) D E) C and E
Using the CPM,which activities have slack in this project?