A Project Consists of Four Consecutive Tasks That Have Average

question 13

Multiple Choice

A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table.Use Goldratt's model to determine the aggregated buffer for this project.  Activity  Average  Worst-Case A1020B1525C2030D2535\begin{array} { | l | l | l | } \hline\text { Activity } & \text { Average } & \text { Worst-Case } \\\hline\mathrm { A } & 10 & 20 \\\hline\mathrm { B }& 15 & 25 \\\hline \mathrm { C } & 20 & 30 \\\hline \mathrm { D } & 25 & 35 \\\hline \end{array}


Definitions:

Selling Price

The amount a buyer pays to purchase a product or service from a seller.

Variable Cost

A cost that varies with the level of output or production, such as materials and labor directly involved in manufacturing.

Fixed Costs

Expenses that do not change with the level of goods or services produced by a business, such as rent or a salaried employee's wages.

Variable Costs

Expenses that change in proportion to the activity or volume of production, sales, or services rendered.

Related Questions