A Project Is Represented by the Activity Durations (In Days,estimated

question 12

Multiple Choice

A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the project buffer if this project is managed using critical chain methodology? Use the rule of thumb approach.  Activity  Predecessor  Lengenth  Activity  Predecessor  Length  A 18EC,D13B16FC9CA22GE,F15DB14\begin{array} { | l | l | l | l | l | l } \hline \text { Activity } & \text { Predecessor } & \text { Lengenth } & \text { Activity } & \text { Predecessor } & \text { Length } \\\hline \text { A } & - - & 18 & \mathrm { E} & \mathrm { C }, \mathrm { D} & 13 \\\hline B & - & 16 & \mathrm { F} & \mathrm { C }& 9 \\\hline \mathrm { C } & \mathrm { A } & 22 & \mathrm {G} & \mathrm { E } , \mathrm { F } & 15 \\\hline \mathrm { D } & \mathrm { B } & 14 & & & \\\hline\end{array}


Definitions:

Career Paths

The progression or sequence of occupations and roles that an individual undertakes throughout their working life.

Women of Color

A term used to describe female individuals of non-white racial or ethnic backgrounds, often highlighting their unique experiences and challenges.

Workplace Strains

The stresses and pressures experienced by individuals in their job environments, including workload, interpersonal conflicts, and job security concerns.

Mentoring

A relationship in which a more experienced or knowledgeable person helps to guide a less experienced or knowledgeable person, often career or educationally focused.

Related Questions