question 87

Essay

Given the network diagram above,determine each of the following:
(i)the activities which are on the critical path
(ii)the expected project duration
(iii)the probability that the project will be completed in 29 weeks or less
(Note:
the numbers on each node refers to the expected duration and standard deviation in weeks for that activity.
E.G., 8,2 indicates an expected duration of eight and a standard deviation of two weeks.)
Given the network diagram above,determine each of the following: (i)the activities which are on the critical path (ii)the expected project duration (iii)the probability that the project will be completed in 29 weeks or less (Note:  the numbers on each node refers to the expected duration and standard deviation in weeks for that activity. E.G., 8,2 indicates an expected duration of eight and a standard deviation of two weeks.)


Definitions:

Cover Message

A written communication sent along with another document (such as a resume) to provide additional information or to introduce oneself.

Job Interview

A formal meeting between a job applicant and an employer or panel, aimed at evaluating the applicant's suitability for a position.

Cover Message

A letter or message that accompanies and introduces another document, such as a résumé, explaining its purpose or relevance.

Visual Résumé

A visual résumé presents an individual's professional background and skills through creative and graphical elements, such as charts, images, and infographics, rather than through a traditional text-based format.

Related Questions