Examlex

Solved

You Have Determined That a 75 Percent Learning Curve Is

question 7

Multiple Choice

You have determined that a 75 percent learning curve is appropriate for a task. If the initial timing of the person performing that job was 50 minutes, and if you need the job performed 500 times, how many minutes of work will be required?


Definitions:

Information Technologies

The use of computers, software, and telecommunications to store, retrieve, transmit, and manipulate data, often in the context of business operations.

Agriculture

Engaging in agriculture by working the earth, cultivating plants, and rearing animals to supply food, fiber, and more.

Parity Concept

In economics, it refers to the idea that two currencies are at par when their exchange rates allow for the purchase of the same quantity of goods in both countries.

Criticism

The practice of evaluating, analyzing, or assessing something or someone often with a focus on identifying faults or shortcomings.

Related Questions