A Project Has the Activity Duration and Cost Information Indicated

question 6

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 32 weeks.What is the cost of the least expensive project possible?  Activity  Normal  time  Crash  time  Normal  Cost  Crash  Cost  Predecessor A85$1,0002,000B641,5002,000 A C851,8002,300 AD1291,0001,800 BE14119501,450 BF971,5001,900 C, D G752,3002,800 E, F \begin{array} { | l | l | l | l | l | l | } \hline \text { Activity } & \begin{array} { l } \text { Normal } \\\text { time }\end{array} & \begin{array} { l } \text { Crash } \\\text { time }\end{array} & \begin{array} { l } \text { Normal } \\\text { Cost }\end{array} & \begin{array} { l } \text { Crash } \\\text { Cost }\end{array} & \text { Predecessor } \\\hline \mathrm { A } & 8 & 5 & \$ 1,000 & 2,000 & \\\hline \mathrm { B } & 6 & 4 & 1,500 & 2,000 & \text { A } \\\hline \mathrm { C } & 8 & 5 & 1,800 & 2,300 & \mathrm {~A} \\\hline \mathrm { D } & 12 & 9 & 1,000 & 1,800 & \mathrm {~B} \\\hline \mathrm { E } & 14 & 11 & 950 & 1,450 & \mathrm {~B} \\\hline \mathrm { F } & 9 & 7 & 1,500 & 1,900 & \text { C, D } \\\hline \mathrm { G } & 7 & 5 & 2,300 & 2,800 & \text { E, F } \\\hline\end{array}


Definitions:

Individual Action

Actions or deeds carried out by a single person that can influence or impact their environment or society.

Microstructural Level

Refers to the analysis focused on the smallest units of society, such as individuals and their interactions, in contrast to larger societal structures.

Social Life

The part of an individual's time that is spent interacting with others, contributing to their sense of belonging and community.

Roommates

Individuals living in the same housing unit without being related by blood or marriage.

Related Questions