The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the expected time to complete the project is A) 34.17 weeks. B) 33.23 weeks. C) 31.00 weeks. D) 21.67 weeks.
Table 9.2
-Using Table 9.2,the expected time to complete the project is