Table 310
You Are Responsible for Managing a Project with the the Following

question 50

Multiple Choice

Table 3.10
You are responsible for managing a project with the following activities
(times are given in weeks) .
 Activity  Optimistic  Time  Most Likely  Time  Pessimistic  Time  Immediate  Predecessor(s)   A 2514 B 81114 C 579 A  D 6912 A  E 135 D,B \begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Optimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Most Likely } \\\text { Time }\end{array} & \begin{array} { c } \text { Pessimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \text { A } & 2 & 5 & 14 & \cdots \\\text { B } & 8 & 11 & 14 & \cdots \\\text { C } & 5 & 7 & 9 & \text { A } \\\text { D } & 6 & 9 & 12 & \text { A } \\\text { E } & 1 & 3 & 5 & \text { D,B } \\\hline\end{array}
-Using Table 3.10,which activity has the largest slack,and how large is that slack?


Definitions:

December 31

December 31 is the last day of the year in the Gregorian calendar, often associated with closing the annual accounting period for businesses.

Board of Directors

A group of elected or appointed members who jointly oversee the activities of a company or organization.

Stockholders

Individuals or entities that own shares of stock in a corporation, giving them rights to dividends and a vote in company matters.

Policies

Statements of principle and guidelines, formulated or adopted by an organization, to direct and limit actions in pursuit of its objectives.

Related Questions