Consider the Following Project -What Is the Latest Time That Activity B Can Finish

question 104

Multiple Choice

Consider the following project.
 Activity  Imunediate  Predecessor  Activity Time  (drys)   A 3B4CA4DA6EB5FC,D4GEFF7\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Imunediate } \\\text { Predecessor }\end{array} & \begin{array} { c } \text { Activity Time } \\\text { (drys) }\end{array} \\\hline \text { A } & - - & 3 \\\hline \mathrm { B } & - - & 4 \\\hline \mathrm { C } & \mathrm { A } & 4 \\\hline \mathrm { D } & \mathrm { A } & 6 \\\hline \mathrm { E } & \mathrm { B } & 5 \\\hline \mathrm { F } & \mathrm { C } , \mathrm { D } & 4 \\\hline \mathrm { G } & \mathrm { E } _ { \mathrm { F } } \mathrm { F } & 7 \\\hline\end{array}
-What is the latest time that activity B can finish without delaying any other activities?


Definitions:

Reflect

To think deeply or carefully about something, often involving a critical examination of past actions or events.

Merit Pay

Merit pay is a compensation approach that rewards employees based on their performance as assessed through evaluations, aiming to encourage higher levels of output.

Developmental Reasons

Underlying causes or motives related to growth, progress, or change in an individual or organization.

Performance Appraisals

The evaluation process through which employee performance is assessed, typically on an annual or semi-annual basis.

Related Questions