Table 7.7
A company makes four products that have the following characteristics: Product A sells for $75 but needs $20 of materials and $20 of labor to produce;Product B sells for $90 but needs $45 of materials and $20 of labor to produce;Product C sells for $110 but needs $50 of materials and $30 of labor to produce;Product D sells for $135 but needs $75 of materials and $40 of labor to produce.The processing requirements for each product on each of the four machines are shown in the table. Work centers W,X,Y,and Z are available for 40 hours per week and have no setup time when switching between products.Market demand is 50 As,60 Bs,70 Cs,and 80 Ds per week.In the questions that follow,the traditional method refers to maximizing the contribution margin per unit for each product,and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 7.7.Using the bottleneck method,in what sequence should products be scheduled for production?
Subsistence Needs
Fundamental requirements necessary for individuals to maintain their basic living conditions, such as food, shelter, and clothing.
Thrill Of Entering
The excitement or exhilaration experienced when engaging in or embarking on something new or adventurous.
Expressive Needs
Human desires or motivations to express oneself emotionally or creatively, often through art, communication, or personal style.
Technical Skills
Abilities and knowledge needed to perform specific tasks, often relating to computational and physical technology.
Q4: Use the information from Table 7.15 to
Q9: A line balance that is 100% efficient
Q25: Use the information in Table 7.9.What is
Q39: The _ determines the frequency and quantity
Q75: The single,multiple,and finite waiting line models all
Q86: Instead of dividing by nc to determine
Q108: Use the information in Case 8.3.How many
Q115: What is Little's Law? How might it
Q158: Wider limits on a control chart result
Q160: _ is the philosophy that waste can