A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days) shown in the table below.Complete the table and determine the expected completion time for the project. A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days) shown in the table below.Complete the table and determine the expected completion time for the project.   A) 17 days B) 18 days C) 21 days D) 19 days


Definitions:

National Defense

Represents the government's actions and policies aimed at protecting its country from external threats, typically involving military and defense strategies.

Excludable

A characteristic of a good or service that allows its owner to prevent others from using it without permission.

Rival In Consumption

A term indicating that the consumption of a good or service by one person diminishes the ability of another person to consume the same good or service.

Tragedy

Tragedy is a form of drama based on human suffering that invokes an accompanying catharsis or pleasure in audiences.

Related Questions