Table 5.2
A company makes four products that have the following characteristics: Product A sells for $75 but needs $20 of materials and $20 of labor to produce; Product B sells for $90 but needs $45 of materials and $20 of labor to produce; Product C sells for $110 but needs $50 of materials and $30 of labor to produce; Product D sells for $135 but needs $75 of materials and $40 of labor to produce. The processing requirements for each product on each of the four machines are shown in the table.
Work centers W, X, Y, and Z are available for 40 hours per week and have no setup time when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In the questions that follow, the traditional method refers to maximizing the contribution margin per unit for each product, and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 5.2. Using the traditional method, in what sequence should products be scheduled for production?
Q29: Lucy's Pancake House, a no-frills diner along
Q60: Assume that activity G has the following
Q66: The just-in-time (JIT) philosophy is the belief
Q76: _ is a qualitative lean tool for
Q88: Heidi was part of a project team
Q109: There are three consecutive steps in a
Q118: Assuming a beta distribution is being used,
Q137: A discount store is experiencing an unacceptable
Q161: A manufacturer embarking on a Six Sigma
Q215: Brainstorming sessions can be effectively conducted on