Consider the Following Work Breakdown Structure

question 111

Multiple Choice

Consider the following work breakdown structure:
Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity E? A) 0 week B) 1 week C) 2 weeks D) 3 weeks E) 4 weeks
What is the estimated standard deviation in the time for activity E?